Instantly calculate statutory construction holdback (10%, 7.5% in Manitoba, 15%/20% in PEI, or contractual in Quebec), net progress draw payable, GST/HST timing under Excise Tax Act s. 168(7), accumulated holdback to date, and generate a clean Progress Claim PDF.

1. Province & Progress Draw Inputs

Prompt Payment and Construction Lien Act (Alberta)

Alberta applies a 10% statutory holdback. Note the extended 90-day lien registration and holdback period for ready-mix/precast concrete work and oil & gas well sites. Progressive/annual holdback release applies to qualifying multi-year contracts over $10M.

Contractor, Client & Project Details (For PDF Certificate)
PROGRESS CLAIM & HOLDBACK CERTIFICATE · AB

Chinook Structural & Contracting Ltd.

CRA GST/HST No: 84920 1142 RT0001

Progress Draw #04

Claim Date: 2026-10-29

Jurisdiction: Alberta

Project / SiteFoothills Industrial Warehouse — Phase 2
Billed To (Owner / Payor)Bow River Developments Corp.

A. Current Progress Claim & Statutory Holdback Breakdown

Gross Work Completed This Period (Pre-Tax)$85,000.00 CAD
Less: Statutory Holdback Retained (10%)− $8,500.00 CAD
Net Progress Draw Payable Now (Pre-Tax)$76,500.00 CAD
Add: GST (5%) on Payable Portion (ETA s.168(7))+ $3,825.00 CAD
TOTAL PAYMENT DUE THIS CLAIM (INCL. TAX)$80,325.00 CAD

B. Cumulative Contract & Holdback Summary To Date

Total Contract Value$450,000.00 CAD
Total Billed To Date (58.9%)$265,000.00 CAD
Remaining Unbilled$185,000.00 CAD
Prior Holdback Held$18,000.00 CAD
Accumulated Holdback To Date$26,500.00 CAD
Deferred Tax on This Holdback$425.00 CAD

CRA GST/HST Timing Rule (ETA s. 168(7)): Under subsection 168(7) of the federal Excise Tax Act, GST/HST on a statutory construction holdback becomes payable on the earlier of the day the holdback is paid/released or the day the holdback period expires.

Provincial Lien Window (Alberta): 45 days standard · 90 days for concrete & oil/gas well improvements.

Generated by Alberta Studio — Free Tools · albertastudio.devFor informational purposes only · Verify with current statute

Export Official Progress Claim PDF

Zero watermark clutter — formatted for single-page A4/Letter printing.

Automated Progress Billing & Contractor CRM

Want this calculated automatically across all your jobs? Check out Buildric.

Buildric tracks estimates, progress draws, holdback release reminders, missed-call SMS text-back, and client follow-ups for Canadian trade contractors — flat-rate from $297 CAD/mo.

Disclaimer: Provided for informational and estimating purposes only. Does not constitute legal or tax advice. Always verify statutory holdback percentages, prompt payment timelines, and lien registration deadlines against current provincial legislation and your construction contract.